Sheyenne Street Segment 2 - Beaton Dr. to 32nd Ave

Sheyenne Street Segment 2 Finished Section Rendering

About this Project

Reconstruction of Sheyenne Street from Beaton Drive to 32nd Avenue to increase roadway capacity from one lane in each direction to three lanes in each direction. Includes installation of traffic signals at major intersections. The project coincides with I-94 interchange reconfiguration project.

Estimated Construction Cost

  • $24 million (partially funded by ND DOT)

Estimated Special Assessments

  • $2,000-$3,000 for residential properties with less than 2 acres
  • Assessment for costs associated with segments 2 and 3

Project Schedule

  • Estimated Start Date: June 2018
  • Estimated End Date: October 2019
  • Project completion: 40%

Road Closures

  • Current traffic pattern:
    • Open to three lanes of traffic in each direction south of 26th Avenue W.
    • Open to one lane of traffic in each direction north of 26th Avenue W. and utilize the existing Diversion Bridge.
    • One lane of traffic in each direction will continue through the interchange until Beaton Drive.
  • Current intersection closure:
    • 24th Avenue W. and Sheyenne Street intersection is closed to access Sheyenne Street. Traffic shifted to the east side of the roadway between the Sheyenne Diversion channel bridge to 26th Avenue W. intersection.
  • OVERNIGHT CLOSURE: An overnight road closure is scheduled for the Sheyenne Diversion Channel Bridge Wednesday, April 24. Crews will close Sheyenne Street at 8 p.m. to all traffic between 26th and 21st Avenues W. until 6 a.m. Thursday, April 25, to safely complete a bridge deck pour. The road closure is necessary because oversized equipment will be placed on Sheyenne Street to pour the new southbound diversion channel bridge deck. By the early morning rush hour Thursday, both directions of Sheyenne Street will be open to drivers in this stretch and the current work zone traffic patterns will resume.0_overnight_closure_diversion_bridge_Sheyenne_map_a5 Opens in new window

Completed Work

  • Lift station sheeting
  • Temporary pipe crossings

Current Work

  • Sanitary sewer force main at diversion channel
  • Water main relocations

Upcoming Work

  • Reduced Lanes: 32nd Avenue W. intersection traffic will shift to the north side with one lane in each direction. Crews will begin the remaining underground and installation of permanent traffic signals in the southeast and southwest quadrants. Local access will continue to use 32nd Avenue W. and Sheyenne Street intersection to travel south to side streets.

Overview Map

Overview map of Sheyenne Street segment 2 reconstruction as of April 22