Citywide Concrete Repair Project

Current Schedule Information:

In Progress

  • AREA G, reopening Oct. 20
  • AREA I, reopening Oct. 21
  • AREA H, reopening Oct. 25
  • AREA K, reopening Oct. 25

  • All areas scheduled for completion on or before Oct. 25, 2022
    *Click into map to zoom and expand 

Work Areas

AREA Approximate Location
A 9th St. NW from Main Ave. to 12th Ave. NW
B 3rd Ave. NW and 1st Ave. NW from 26th St. NW to 21st St. NW
C Main Ave. W from 19th St. E to 17th St. E
D 7th Ave. E from 9th St. E to 17th St. E
E 13th Ave. W from 8th St. W to Sheyenne St.
F E Beaton Dr. from Veteran’s Blvd. to W Beaton Dr. 
G 3rd Ave. E from 6th St. E to Bluestem Dr. E
Intersection of 4th St. E and 26th Ave. E
7th St. E from 31st Ave. E to 26th Ave. S
H Intersection of 31st Ave. E and Bluestem Dr. E
32nd Ave. E from 4th St. E and Veteran’s Blvd.
I 4th St. E from 35th Ave. E to 40th Ave. S
J 9th St. W from Mulberry Ln. to 47th Ave. W
K 9th St. W from Albert Dr. W to 8th St. W