Sheyenne Street Segment 1 - 13th Ave. to Beaton Dr

Sheyenne Street Segment 1 Finished Section Rendering

About this Project:

Reconstruction of a five-lane road that includes two lanes in each direction and a center turn lane to ease congestion and safety concerns. Project work includes concrete paving, curb and gutter, shared-use path, city utilities, street lights and traffic signal improvements.

Estimated Construction Cost

  • $6 million

Estimated Special Assessments

Project Schedule

  • Estimated Begin: April 2018
    • Phase 1 completion – early July
    • Phase 2 completion – early September
    • Phase 3 completion – mid September
    • Phase 4 completion – early October
  • Estimated End: October 2018
  • Project complete: 2%
Sheyenne Street public impacts June 7

Expected Road Closures

  • Traffic shifted to one lane each of north- and southbound traffic in the existing west side of the road.
  • Access to Beaton Drive closed at Sheyenne Street. Motorists can use Ninth Street East to enter and exit Beaton Drive.
  • Access to enter and exit Sheyenne Street at 17th Avenue W. closed Thursday, June 7, for storm sewer installation.
  • Water turned off for properties on located on the west side Sheyenne Street from Rue Avenue to 19th Avenue W. This is only for properties located on Sheyenne Street.
  • Congestion and delays likely during peak traffic

Other Impacts

  • Portion of trees removed and/or trimmed on both sides of Sheyenne Street
  • Utility locate flags are placed along 13th Avenue to help crews on site trace utilities if issues occur during the project

Completed Work

  • Some pavement removals
  • Temporary signals
  • Temporary asphalt bypass installed
  • Installation of first two storm outfall structures

Current Work

  • Underground utility line (power, fiber optic, cable, gas) relocation
  • Storm sewer installation

Upcoming Work

  • Underground utilities